Pan-Century Edible Oils (PCEO) Sdn Bhd, a manufacturer
of oil refinery products and specialty products, is
one of the 48 factories audited by the MIEEIP team
under the Energy Audit Programme. The factory's monthly
energy bill amounts to RM2 million. The aim of the
audit is two folded, namely, to identify energy cost
saving potentials and transfer the auditing skill
to the staff of PCEO. Jointly, the MIEEIP audit and
the PCEO energy management teams identified several
potential energy cost saving measures. A combination
of measures recommended by the MIEEIP and PCEO's energy
teams on steam management, cooling tower modification,
energy-use monitoring and targeting, and the replacement
of standard motors to high efficiency motors are discussed
here as local case studies for industrial energy efficiency.
PLANT
OVERVIEW
PCEO commenced its operations in Malaysia
25 years ago, and to date has 13 plants at a single
location in Pasir Gudang, Johor. Its total manufacturing
capacity of oil refinery products and specialty products
is about one million tonnes. The factory recorded
an annual turnover of RM 750 million in 2002. This
internationally recognised company, which is a member
of the Aditya Birla Group, has a workforce of 285
people
The company had already established a Focused Improvement
Project Team (FIPT) prior to the collaboration with
MIEEIP. FIPT, which was tasked with overall improvement
strategies, responded positively to several MIEEIP
recommendations on steam management and implemented
them systematically. Its initiatives on other energy
efficiency improvement areas are ongoing and closely
monitored for comparisons against established norms
under the in-house Purta or benchmarking system
PROJECT
OVERVIEW
More than 550 tonnes of steam is generated
daily for physical refining, making soap noodles,
tank farm heating and fractionation. During the audit,
the team identified significant steam leakages and
analysed the respective losses. To minimise these
losses and to implement other energy cost saving measures,
the management embarked on an RM 1.0 million venture.
To date, the steam optimisation programme has alone
resulted in an annual energy saving of RM680,481.
Other measures that were already initiated by PCEO
are modifications to the factory's cooling towers;
replacement of standard motors with high efficiency
motors; steam conversation schemes heat recovery schemes
and monitoring & targeting, which produced a total
energy savings of RM320,000. PTM has agreed to do
the study of compressed air system and chilled water
system.
Project
One: Steam System Optimisation
Background
PCEO
operates four units of boilers to supply steam to
the refining and soap noodle plants. Steam is generated
at a cost of RM50 per metric tonne, whereby 90 percent
of the cost component is for fuel purchase while maintenance,
chemical treatment and water consumption make up the
balance 10 percent. About 55 KL per day of Medium
Fuel Oil (MFO) is consumed. Realising the immense
benefits of the energy saving measures and in view
of the increasing fuel and water costs, PCEO embarked
on a holistic approach to optimise the existing steam
supply and demand structure. Steam saving target was
set at 10 percent and to facilitate this, the FIPT
immediately got to work to further confirm and implement
the energy saving measures.
Project
Implementation
The
energy saving measures identified by the team for
the steam supply and demand system were divided into
no, low, and high cost categories. PCEO used both
its in-house financial resources and expertise to
implement the identified Energy Cost Reduction Measures
(ECRMs) in stages since May 2002. The high commitment
and seriousness showed by factory's top management
ensured the full completion of the projects within
an eight-month period. Through monitoring and verification,
the savings were quantified and reviewed on a monthly
basis for the following measures:
I. Use of low pressure steam (3.5 barg) for tank farm
heating and tracing lines in place of medium pressure
steam (14.5 barg)
Audit findings: The maximum temperature required
for tank farm heating and tracing lines is between
70 and 80 degrees centigrade, which can be attained
with low-pressure steam.
Measure recommended: To convert the current
heating system heating to low pressure.
Action taken: The present medium pressure header
was provided with pressure regulating valves to supply
low-pressure steam for tank farm heating.
II. Installation of pressure regulating valves for
steam to distillation vacuum plant
Audit
findings: The design vacuum pressure for the distillation
plant is 10 barg at a steam header pressure of 13.5
barg. This combination of settings resulted in higher
steam consumption amounting to 24 percent.
Measure recommended: To supply the steam at
an optimum pressure of 10 barg.
Action taken: Pressure regulating valves were
installed in the vacuum circuits to maintain the steam
supply pressure at 10 barg.
III.
Insulation improvement
Audit
findings: An insulation survey for the entire
plant was carried out to identify areas of insulation
losses. It was found that many steam lines were not
properly insulated.
Measure
recommended: To carry out an audit of the steam
distribution system to determine the various sizes
of insulation to minimise the losses and rectify the
steam leakages.
Action taken: All condensate return lines,
valves, and fittings were provided with correctly
sized insulation to prevent heat losses. The temperature
difference between the pipe surface and the ambient,
maintained at around 10OC after the rectification,
not only saves energy but also creates a thermal-comfort
working environment.
IV.
Steam trap maintenance
Audit findings: Steam traps were found either
under sized or leaking due to the lack of maintenance.
This in turn contributes to the ineffectiveness of
the entire steam distribution system.
Measure
recommended: Conduct a survey on the existing
steam traps and replace the under sized ones, and
establish a steam trap periodic maintenance system.
Action taken: Suitable sized traps were provided
and a strict steam trap checking procedure was implemented
to detect faulty traps before installation.
V.
Condensate recovery
Audit
findings: The steam condensates at the various
points of use were not recovered, because of possibility
of oil contamination. This again contributes to the
low efficiency of the combined boiler and steam distribution
system
Measure
recommended: Pipe all the condensates to suitably
installed intermediate tanks before transferring them
to the soft tank for reuse in the boilers.
Action taken: Intermediate tanks and a pump
were installed to collect and transfer the condensate
to the existing soft water tank for reuse in the boilers.
This resulted not only in fuel savings but also savings
in water treatment chemicals.
VI.
Temperature control for heating tanks
Audit
findings: Although the required heating temperature
of the tank farms is only 80oC, due to continuous
charging of the steam the temperature raises up to
95oC. The rise between 80oC and 90oC not only contributes
to energy wastage but also affects the quality of
the contents of the tank farm.
Measure
recommended: A temperature controller system should
be provided to ensure no excess steam is charged to
the tank farm.
Action
taken: A temperature controller system to cut
in and out the steam charging at 78oC and 80oC respectively
was installed. This can be considered as good energy
management practice.
VII. Replacement of steam ejectors with vacuum pump
in PC1 bleacher unit
of medium pressure steam (14.5 barg)
Audit findings: It was noticed that steam ejectors
were used to create the 70 Torr vacuum pressure in
the bleacher. This indirect method of converting steam
pressure to create vacuum is highly energy inefficient.
Measure
recommended: Outsource for suitable system that
will create direct vacuum pressure.
Action
Taken: A water seal ring type vacuum pump, which
is a proven energy efficient method for creating vacuum
pressure, is installed
Results
The
energy and cost savings as well as the CO2 reduction
achieved from the implementation of the above ECRMs
is shown in the following table. On the whole, steam
consumption at PCEO was reduced to 35 metric tonnes/day
from the above schemes.
Table 1: Summary of energy savings.

Project
Two: Cooling Tower Modification
Background
Seven
cooling towers are located strategically in the fractionation,
physical refining and soap noodles plants. Cooling
water is used mainly in crystallisers, heat exchangers
for cooling process fluids, compressor intercoolers
and after coolers and condensers. The performance
of the cooling towers in the fractionation plant was
investigated and it was found that energy savings
of 25 percent could be achieved by implementing thermal
efficiency improvement measures in this area.
Project
Implementation
The
following weaknesses were found at the cooling towers:
I.
The cooling towers were designed for 38oC return water
temperature and 30oC cold-water temperature at 27oC
wet bulb temperature. However, as against design temperature
drop of 8oC, the actual cooling was 5oC at 26oC wet
bulb temperature. Therefore, the cooling load achieved
was only 60 percent of the design capacity.
II.
The liquid to gas (L/G) ratio was at 0.8 and 0.86
for cooling tower no.1 and 2.67 for cooling tower
no.2. The recommended L/G ratio for tropical climatic
condition is between 1.0 and 1.1. The L/G ratio can
be improved by increasing the blade angle of the fans
to increase the flow rate.
III.
Due to lower differential temperature, 3 cells were
in use to get the desired heat duty.
The
poor performance of the cooling towers was due to
the condition of the fills and bad distribution of
water. The fills are also broken and displaced from
their position due to sagging. The combined effect
of these defects streams the water through the cooling
tower instead of being broken into fine particles,
which is a pre requirement for efficiency in heat
removable from the returned hot water.
The
improvements to the cooling towers are being carried
out in phases. The existing seven wooden fills were
replaced with PVC fills whereas the FRP fan blades
have replaced aluminium fan blades as they are lighter
and provide effective blade angle management. The
blade angle of the fan was fixed at around 16o to
maintain an optimum air velocity of 9m/s.
Results
Due
to the above modification in cells of cooling tower,
the differential 20 temperature improved from 5°C
to 7°C and one cell fan was stopped resulting
in net power saving of 20 kW, equivalent to RM 35,000/year.
Project
Three: High Efficiency Motors
Background
High
Efficiency Motors (HEMs) are generally two to four
percent more energy efficient than standard motors.
The paybacks on HEMs are high when they are incorporated
during the initial installation stages of the plant.
However, replacing an exiting standard motor just
before its life cycle can justify the HEM option.
Apart from this, HEMs can be considered as a preference
instead of rewinding an existing standard motor. Usually
the loss in efficiency resulting from rewinding amounts
to two to three per cent.
Project
Implementation
At
PCEO, a programme to replace the existing standard
motors to HEMs was started in 1994 in a phased manner.
The replacement was done in stages and as of today,
most of the standard motors in the all plants have
been replaced by HEMs. Though the purchase price of
HEMs is about 20 percent more, PCEO achieved a significant
decrease in the electricity consumption over the years.
According to them, the top management was instrumental
in the success of this programme, as they believed
the additional price (or premium) could be repaid
by the energy cost savings from the motors with higher
efficiencies.
The
economic feasibility of investing in a new HEM is
calculated using a common method called "simple
payback".

An
example of such calculation is shown in the table
below for one of the existing standard motors that
was replaced recently.

The
total investment cost for the replacement of all the
existing standard motors to HEMs was RM400,000. This
investment was quickly recovered within four years.
The
total investment cost for the replacement of all the
existing standard motors to HEMs was RM400,000. This
investment was quickly recovered within four years.
Project
Four: Energy Monitoring & Targeting
Background
As a management driven activity, the
company has implemented a Monitoring and Targeting
(M&T) system to support the Birla Group's World
Class Manufacturing (WCM) philosophy - If you can't
measure, then you can't manage. According to Pan-Century's
joint president Mr. S.C Jain, the M&T exercise
directly detects abnormalities for immediate remedial
actions. This in turn results in energy savings, which
otherwise would not have been realised due to the
delay in detection of the same manually.
Norms
are established for consumption trends and weekly
targets are set and monitored closely. Every month,
the established figures are compared against the actual
consumption or output at the management meetings.
Follow up actions for abnormalities are addressed
in the meetings. The findings and the analysis of
the data gathered from the M&T system are reported
to the headquarters for further scrutiny. If targets
are not met, justification is sought and peer factories
will be contacted for assistance. Otherwise, the company
strives to improve its operations to meet the set
targets.
Project
Implementation
The
M&T system is part of the parent company's Purta
system, which has been in practice for years in all
aspects of manufacturing and performances. It is a
benchmarking system established based on design point
consumption values. These are ideal values computed
for every set of production parameters such as material
inflow, product output, utility consumed and waste
generated. At PCEO, M&T is carried out at both
plant wide and each sub-process levels. Below is a
sample of the M&T format.

The
company is in the midst of completing the installation
of an online monitoring system for energy consumption.
Phase One of the project has been completed with the
installation of the metering equipment at every supply
and consumption point. The second phase, involving
the centralisation of the electronic energy data feedback
and reporting system through local network, is ongoing.
The company has purchased several metering equipment
such as the maximum demand controller, which was installed
in April 2003; kWh meters; steam flow meters and the
chiller load controller. Installation is being done
in-house.
The
total cost of metering is approximately RM17,000 for
the maximum demand controller (RM3,000); steam flow
meter (RM12,000 per unit) and chiller load manager
(RM 2,000). No expenses were incurred for the installation
and commissioning or the development of the M&T
software as they were done entirely by the staff.
Results
M&T
enables the company to monitor and verify the implemented
energy saving measures and control energy and material
wastage. In a short span of time, monitoring via the
maximum demand controller resulted in more vigilance
over energy consumption and immediate corrective actions,
such as switching off the non-critical load.
|
Management-driven commitment towards EE
At
a recent interview, Pan-Century vice president
(Engineering) Mr. P. R. Goyal explained that
energy efficiency is deployed through the company's
policy to attain total customer satisfaction
at minimum cost. He said: "Energy, which
cost the company RM2 million monthly, is one
of the cost components that can bring maximum
return on investment related to energy efficiency.
We are also committed to a greener environment
through the efficient use of natural resources,"
Mr. Goyal added.
This high level commitment was
affirmed by Mr. Jain. He explained that the
management would approve EE projects even though
some of them had long payback periods. He said
the determining factor in approving such projects
is the potential for plant improvements as well
as the contributions towards social and environmental
benefits. The company has approved self-financing
for many low- and high-cost EE improvement projects
in the past. Now the company is totally convinced
that such projects are not only viable but also
beneficial to the company. Mr. Jain emphasised,
"There are no restrictions to the budget
allocation. As long as we are convinced of the
overall benefits to the company, an energy efficiency
project will be approved immediately."
|
back...