The boiler blowdown process involves
the periodic or continuous removal of water from a
boiler to remove accumulated dissolved solids and/or
sludges. During the process, water is discharged from
the boiler to avoid the negative impacts of dissolved
solids or impurities on boiler efficiency and maintenance.
However, boiler blowdown wastes energy because the
blown down liquid is at about the same temperature
as the steam produced. Much of this heat can be recovered
by routing the blown down liquid through a heat exchanger
that preheats the boiler's makeup water. A boiler
blowdown heat recovery project at Augusta Newsprint
Company's Augusta, Georgia, mill saves almost RM 117,800
annually in fuel costs.
PLANT
OVERVIEW
The Augusta Newsprint mill is part
of a joint partnership between Abitibi Consolidated
and the Woodbridge Company, Ltd. The mill produces
up to 440,000 metric tons of standard newsprint each
year from southern pine and recycled newspaper and
magazines. The mill has 2 paper machines and employs
380 workers.
Abitibi-Consolidated is a global
leader in newsprint and uncoated groundwood papers
with ownership interests in 27 paper mills in Canada,
the United States, the United Kingdom, and Asia (including
its 50 percent interest in Pan Asia Paper Company).
The company also has ownership interest in 22 sawmills,
2 remanufacturing facilities, and a market pulp mill.
Abitibi-Consolidated employs approximately 18,000
people and supplies products in nearly 100 countries.
PROJECT
OVERVIEW
Blowdown is essential for continued
operation of any steam boiler. However, blowdown represents
an energy loss to the steam system. Although the blowdown
rate at Augusta Newsprint is typical of most boilers,
recovering the heat resident in the blowdown stream
can save energy. Currently, the continuous boiler
blowdown is routed to a flash tank where the pressure
is reduced from 20 bar gauge (barg) to approximately
4 barg. Flash steam produced in the pressure reduction
process is piped into the deaerator to offset deaeration
steam demand. This operation is currently saving the
mill about RM 38,000 per year in fuel costs. Additional
energy can be recovered from the contaminated condensate
exiting the flash vessel. The condensate dissipates
energy that could be utilized to preheat makeup water.
Figure 1 shows a schematic of the boiler blowdown
system before and after heat exchanger installation.
PROJECT
IMPLEMENTATION
As water evaporates within a boiler, dissolved solids
in the water are left at the bottom of the boiler,
resulting in buildup of sludge and scale. This buildup
is alleviated by discharging some boiler water through
a valve at the bottom of the boiler. High concentrations
of solids can also lead to foaming near the top of
the boiler and result in water hammer, which may damage
piping, steam traps, and process equipment. Skimming
or surface blowdown removes the dissolved solids near
the surface of the liquid and is usually a continuous
process. This flow is routed through a heat exchanger.
The amount of blowdown necessary depends on boiler
operating pressure, amount of makeup water, impurity
levels in the make up water, and the dissolved solids
concentrations that a given boiler can tolerate.
Augusta mill personnel modified the
existing boiler blowdown system to recover the energy
from the continuous blowdown stream from the boiler
blowdown flash tank. Modifications included installing
a plate-and-tube heat exchanger and associated piping
(Figure 1). The 149°C water from the flash tank
drain was routed to the "hot side" of the
heat exchanger to preheat boiler feedwater passing
through the other side of the heat exchanger.
RESULTS
At the Augusta mill, preheating the
boiler feedwater by 10°C will save almost RM 117,800
in annual fuel costs. These calculations are based
on a normal feedwater flow of 13 liter per second,
a temperature differential of 10° C, and a fuel
cost of RM 8.85 per 0.5 tonnes of steam. The total
cost of the project is RM 57,000; the simple payback
period is about 6 months. Nearly 14,770 GJ in annual
energy savings are expected.
back...